Configuring the First Day of the Working Week

To configure the First Day of the Week in the Schedule:

  1. Select Schedule Settings in the Main window.

    Figure 5-20 Main Window

    images/1_Main00084_1.gif 

    The Schedule Settings pane of the Main window opens.

    Figure 5-21 Main Window

    images/2_Schedule_Settings00085_1.gif 

  2. Select the Basic Schedule Settings field in the Schedule Settings pane.

    Figure 5-22 Main Window

    images/3_Basic_Schedule_Settings00086_1.gif 

    The Basic Schedule Settings window opens.

    Figure 5-23 Basic Schedule Settings Window

    images/4_Basic_Schedule_Settings_Window00087_1.gif 

  3. Select the arrow in the First Day of Week field.

    Figure 5-24 Basic Schedule Settings Window

    images/13_First_Day_1.gif 

    The First Day of Week dropdown menu opens.

    Figure 5-25 Basic Schedule Settings Window

    images/14_First_Day_Dropdown_1.gif 

  4. Select the required First Day of Week value from the First Day of Week dropdown menu.

    The First Day of Week dropdown menu closes, and the selected First Day of Week value appears in the First Day of Week field.

  5. Scroll down the Basic Schedule Settings window and select Save.

The configuration is saved, and the Data Successfully Saved message appears at the bottom of the Basic Schedule Settings window.



See also:

Modifying the First Day of the Working Week