Home > Schedule Settings > Basic Schedule Settings > Add a Week to Base Date > Modifying an Additional Week to the Base Date Configuration
Modifying an Additional Week to the Base Date Configuration

To modify the Number of Day Templates in a Schedule:

  1. Navigate to: Main>Schedule Settings>Basic Schedule Settings.

  2. Select the Assigning Time Period field.

    Figure 5-60 Basic Schedule Settings Window

    images/15_Assign_Time00113_1.gif 

  3. Modify the Time Period value in the same manner as configuring the Time Period value (to configure the Time Period see Configuring an Additional Week to the Base Date ).

  4. Scroll down the Basic Schedule Settings window and select Save.

The modification is saved, and the Data Successfully Saved message appears at the bottom of the Basic Schedule Settings window.



See also:

Configuring an Additional Week to the Base Date
Deleting an Additional Week to the Base Date Configuration